Summary
Bids for the Whitman Avenue renovation came in over $20 million against $15 million in funding, so all bids were declined. The design will be reworked — stormwater handling was the biggest cost driver, including a $900,000 underground rain barrel — and the project will be rebid.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 25, 2026.
Impact analysis
The project was about $5 million over available funding; redesign costs are expected to be far less than that overage.
Taxpayers benefit from avoiding an over-budget contract while transit service continues.
Construction is delayed pending redesign, though officials said the timeline impact is not significant.