Summary
The annual contract to repaint lane and center lines went to Brickline, Inc. for up to $185,174.65. Staff explained epoxy markings last 8-15 years when applied correctly — unlike the Ballard interchange markings applied in cold weather by the state project.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jul 15, 2026.
Impact analysis
Up to $185,174.65 for the annual striping program.
All drivers who rely on visible lane markings citywide.
Mentions & discussions (2)
Municipal Services Committee — July 15, 2026
The city is hiring Crowley Construction to repaint road markings and parking ramp stripes for up to $43,026.73. Fresher lane lines and crosswalks mean safer, clearer streets for drivers and pedestrians.
Municipal Services Committee — May 11, 2026
The annual contract to repaint lane and center lines went to Brickline, Inc. for up to $185,174.65. Staff explained epoxy markings last 8-15 years when applied correctly — unlike the Ballard interchange markings applied in cold weather by the state project.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Appleton
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.